Your suite is a strip-center space off a county road. The mailing address says Houston, the landlord calls it Houston — and the City of Houston ePermits account shows nothing, because the property was never in the city at all. It is in unincorporated Harris County, which runs its own permit office, its own fire code, and its own version of the paper that lets a business open: a Certificate of Compliance.
That is the first thing to settle when a project looks stuck. Not the plans, not the contractor, not the name of the inspector. Which government is the permit authority for this address.
Settle jurisdiction before you chase anything
The Harris County Fire Marshal’s Office says it straight: it only inspects facilities located within Harris County and outside any city limits — not just Houston’s, any of them. That single line decides who reviews your plans, who inspects your buildout, and who issues the paper at the end. The County’s own address lookup settles it — enter the address and, if the “Law Juris.” column shows Sheriff, the Fire Marshal’s Office is your fire and life-safety contact, not a municipal department.
The County’s Permits Division permits development in the unincorporated area, with a short list of exceptions; its floodplain regulations say so bluntly: development without a permit is prohibited. The City route — counters, ProjectDox status, City inspection scheduling — is a separate stack from county submittals, county review, and county inspectors. Our Houston commercial permit checklist maps the City side.
Reset one expectation too: the County says it does not expedite reviews, and tries to work with customers case by case in emergencies. There is no expedite lever to pull on a county file.
“It was already a restaurant” is not a permit
Harris County requires a Small Tenant Improvement permit for all new and existing tenants occupying space in the shell building. The shell permit is the landlord’s permit. It is not the tenant’s, and it is not permission for the tenant’s use.
The review route then depends on the space and the operation. Express Review is reserved for new, never-occupied spaces of 5,000 square feet or less in mercantile, business, low-hazard storage or low-hazard industrial occupancies, and for existing spaces of that size staying in the same occupancy that are not hazardous or institutional. Plans outside that generally go to Fire Code Review, which can also determine that no review is required at all, and the County handles special circumstances case by case. The submittals differ: Express Review wants a dimensioned floor plan, a site plan, the HCAD number, the shell building permit number, and a completed Express Permit Application; Fire Code Review wants a completed Fire Code Review sheet, dimensioned architectural plans, and a site plan showing fire lane and hydrant locations. Both want a real description of the use — that is how the County classifies occupancy and finds hazards.
The County is also explicit that permits are not issued until plans are approved, absent that no-review determination. A tenant holding an approved shell permit and a signed lease has cleared exactly one of those steps.
The end of the road is a Certificate of Compliance
The certificate is the county’s occupancy paper: the permit office issues it only after a valid permit with all required inspections completed and passed, and after the Fire Marshal’s inspection is approved. The Fire Marshal performs the final inspection when the project is ready for occupancy. The permit fee already includes the review, the final inspection, and the certificate.
The practical sequence, in the usual case, is: approved plans, permit purchased, construction, inspections, Fire Marshal final, certificate request, occupancy. A buildout that looks finished but sits on open inspections is not on the last step — and the first re-inspection is covered by the permit fee, while each later one is a separate $260.
For the city-side version of this bottleneck, see Houston Certificate of Occupancy delays — same failure modes, different departments and paperwork.
The previous tenant’s paper does not travel
A Certificate of Compliance belongs to the business and permit that earned it. The County lists three ways to change the name on an existing certificate:
- The certificate was just issued and its data is wrong because the permit was applied for with bad information: the County’s instruction is to contact its cashiers to correct the permit, then resubmit the certificate request.
- You bought an existing business that has not closed or will not close: sometimes a new certificate can be obtained through the Affidavit for Commercial Establishment process.
- You are a new tenant, or your project does not qualify for that affidavit: a new permit is required for a new certificate to be issued.
A lease takeover that changes the tenant, or a buildout that changes the occupancy, starts a permit — even when the address has been open for years under someone else’s name.
Two deadlines, and a title risk nobody mentions
First deadline: a permit is valid to start construction within 180 days of issuance, or it goes null and void; two six-month extensions can be obtained on written request before it expires.
Second: enforcement in the floodplain context. A structure in violation that is not removed or permitted within the allotted time can end with the County recording a Certificate of Non-Compliance in the Harris County real property records, and the County says that may prevent maintaining a free and clear title. It is a recorded notice that can surface in a title search — which is where a landlord or a buyer meets it.
Opening is not the last permit
Fire code operational permits are a layer of their own: required under Section 105 of the International Fire Code as adopted by Harris County, where the operation falls under them, for a business to operate legally for a stated period. Applications are electronic only, some cannot issue without a passed inspection, and the renewal details are given at issuance. Which permits apply follows what the operation stores, handles, or is — confirm the list for the operation, not for the building type.
So treat the certificate as the door and the operational permits as the standing obligation. A lapse typically surfaces at an inspection, or when a carrier asks.
When you escalate, name the stage: jurisdiction, plan review, an open inspection, the Fire Marshal final, the certificate request, or a renewal. “The city is holding us up” goes nowhere when the city was never the authority.
Unincorporated Harris County permit questions
Does a City of Houston permit cover a suite in unincorporated Harris County?
No. Harris County permits development in the unincorporated area, and the Harris County Fire Marshal’s Office says it only inspects facilities inside Harris County and outside any city limits — not just Houston’s. Confirm jurisdiction with the County’s address lookup before assuming City of Houston tools or inspectors apply.
Can a new tenant reuse the previous tenant’s Harris County Certificate of Compliance?
Not automatically. Harris County lists three ways to change the name on an existing certificate, based on the situation: correcting a certificate just issued from bad permit data, buying an existing business that has not or will not close through the Affidavit for Commercial Establishment process, or — if you are a new tenant or do not qualify for the affidavit — obtaining a new permit so a new certificate can be issued.
Does Harris County expedite plan review?
The County says it does not expedite reviews at this time, and that it tries to work with customers case by case in emergency situations. Express Review is a scope-based track for qualifying small lease spaces, not a paid expedite.
Outside city limits and stuck?
Send the property address, the suite, and the last status you received. We can help work out which government and which stage your file is actually on.